FY 1997 actual | FY 1998 estimated | FY 1999 estimated | |
---|---|---|---|
Total LDRD funding (LANL, LLNL, and SNL) | 184.6 | 190.3 | 204.5 |
Prior years | FY 98 | FY 99-02 | |
---|---|---|---|
SLBM Launcher/SSBN Elimination: | |||
Equipment/Infrastructure | 34 | 6 | 40 |
Elimination efforts (30 submarines) | 35 | 190 | |
Training/Logistics/Program Support | 7 | 4 | 29 |
Liquid Low Level Radioactive Waste Processing | 30 | ||
Missile Elimination | 1 | 7 | 26 |
Total | 42 | 82 | 285 |
Notes.All amounts provided through Nunn-Lugar funding; SLBM = Submarine Launched Ballistic Missile.
1991 | 1992 | 1993 | 1994 | 1995 | 1996 | 1997 | 1998 | 1999 | |
---|---|---|---|---|---|---|---|---|---|
DOE: | |||||||||
Naval Reactors Development1 | 2 | 30 | 119 | 156 | 210 | 169 | 100 | 80 | 55 |
NAVY R&D: | |||||||||
Advanced Nuclear Power Systems | Advanced Nuclear Power Systems | Advanced Nuclear Power Systems | Advanced Nuclear Power Systems | Advanced Nuclear Power Systems | Advanced Nuclear Power Systems | Advanced Nuclear Power Systems | Advanced Nuclear Power Systems | Advanced Nuclear Power Systems | Advanced Nuclear Power Systems |
Advanced Submarine System3 Development | 4 | 23 | 66 |
1The amounts for the formative years are best estimates of the effort leading up to and related to the New Attack Submarine propulsion plant. In this period, which is similar to what the Navy is going through now on CVX, the Program was assessing possible propulsion plant features and the state-of-the-art in various technical areas for applicability, and interfacing with the fleet and activities responsible for other aspects of the ship. Consequently, this was a period of some flux and uncertainty. In setting forth the estimates for the period the effort was made to include the cost of efforts considered specific to the New Attack Submarine propulsion plant.
2Under cognizance of Naval Sea Systems Command (NAVSEA), Code 08, Nuclear Propulsion Directorate.
3Under cognizance of Navy Program Executive Office for Submarines (PEO SUBS) with work performed by NAVSEA, Code 03, Engineering Directorate. Funding is shown only for the period 91-93 to provide reference for the formulation period of the New Attack Submarine. This Program Element covers the Hull Mechanical and Electrical aspects of the ship. This category funded the main turbines, shaft, thrust bearing and the propulsor, i.e. propeller.